1989
Ceasing of plant operations by the owner company (Hifrensa).
1990
Ministerial Order on definitive shutdown and establishing the maintenance conditions for the plant in the safe shutdown condition.
1991
Hifrensa initiates Level 1 dismantling or conditioning tasks.
1994
Submittal by Enresa of the Vandellós I Dismantling and Decommissioning Plan.
1996[/]
Submittal of the Environmental Impact Study.
1997
Environmental Impact Statement. Completion of conditioning or Level 1 tasks.
1998
Approval of the plant Dismantling and Decommissioning Plan.
Transfer to Enresa of ownership of the plant.
Initiation of Level 2 dismantling.
1999
Approval by the Nuclear Safety Council (CSN) of the Active Parts Dismantling Plan and initiation of work.
2000
Confinement and sealing of the reactor shroud.
First shipment of Low and Intermediate Level Wastes from dismantling to the El Cabril centralised disposal facility.
Completion of the Materials Declassification Process Test Plan.
Initiation of works on infrastructures for the dormancy period.
2001
Initiation of shipments of declassified materials to the recycling plants.
Assembly of the reactor shroud outdoor protective structure.
Submittal to the Nuclear Safety Council (CSN) of the Restoration Plan for the released site and documentation required for the dormancy period.
2002
Approval by the Nuclear Safety Council (CSN) of the surface clearance and combined clearance methodology.
Completion of disassembly of the reactor external structures.
2003
Completion of Level 2 Dismantling of the Vandellós I nuclear power plant.
Chronology of the Vandellós I dismantling and decommissioning plan
Última actualización el 01/10/2009
Palabra clave: LILW, low and intermediate level, El Cabril, CSN, chronology, dismantling, decommissioning, dismantling and decommissioning plan, works and operating licence, graphite silos, clearance plan, environmental impact study, materials clearance process, recycling plants, restoration plan for released site, Vandellós I, dormancy