In accordance with the directives of the International Atomic Energy Agency, the Vandellós I nuclear power plant dismantling and decommissioning project is broken down into the following levels:
Interactive
Dismantling of Vandellós I
Schedule: Dismantling of the Vandellós I nuclear power plant step by step
Level 1. Preliminary conditioning activities
Following the definitive shutdown of the plant, the owner company Hifrensa unloaded the reactor, removed the spent fuel, conditioned the operating wastes and removed the wastes stored in the graphite silos.
In addition, the carbon dioxide tanks and main turbine-alternator groups were disassembled.
These tasks were completed between 1991 and 1997.
Level 2. Dismantling of structures
Enresa carried out the Level 2 dismantling of Vandellós I in two phases:
Dormancy period
"The reactor shroud must remain as a regulated area under surveillance for 25 years."
The reactor shroud must remain as a regulated area, restricted and under surveillance for 25 years, the time required for its radioactivity to decay sufficiently for complete dismantling to be addressed.
Level 3. Dismantling of the reactor shroud
The last phase of decommissioning of the plant will be carried out by Enresa on completion of the dormancy period, around 2028, and will consist of removing the reactor shroud and all the internals. The site will then be completely released.
The dismantling and decommissioning of the Vandellós I nuclear power plant step by step
Última actualización el 11/12/2009
Palabra clave: LILW, El Cabril, Vandellós, engineering, quality, surveillance, quality management, environmental management, nuclear fuel, reactor, safety, dismantling, decommissioning, prevention of occupational risk, works and operating licence, graphite silos, structures, active parts dismantling plan, clearance plan, environmental impact study, materials clearance process, mestral, Mestral Technology Centre, IAEA, occupational risk prevention management, technical reports, Vandellós I, dormancy, CMD, technology