Activities and Projects > Dismantling and decommissioning of facilities > Dismantling and decommissioning of the Vandellós I nuclear power plant
...initiates Level 1 dismantling or conditioning tasks.1994.Submittal by Enresa of the Vandellós I Dismantling and Decommissioning Plan.1996Submittal of the Environmental Impact Study.1997.Environmental Impact Statement. Completion of conditioning or...
Activities and Projects > Dismantling and decommissioning of facilities > José Cabrera nuclear power plant decommissioning project
In the Dismantling and Decommissioning Project priority is given to the safety of the personnel performing the work, the general public and the environment.In the Dismantling and Decommissioning Project approved for the José Cabrera nuclear power...
Activities and Projects
...of the spent fuel and its emplacement in the storage installation concluded in 2009.José Cabrera nuclear power plant dismantling and decommissioning plan.Enresa initiated the dismantling work after the Ministry of Industry, Tourism and Trade...
Activities and Projects > Dismantling and decommissioning of facilities
...of the spent fuel and its emplacement in the storage installation concluded in 2009.José Cabrera nuclear power plant dismantling and decommissioning plan.Enresa initiated the dismantling work after the Ministry of Industry, Tourism and Trade...
Activities and Projects > Dismantling and decommissioning of facilities
The Vandellós I nuclear power plant is located in the municipality of Vandellós i L'Hospitalet de L'Infant, in the province of Tarragona. The plant initiated its commercial operation in 1972 under the responsibility of the company Hispano-Francesa...
Activities and Projects > Dismantling and decommissioning of facilities > Environmental Restoration
In 1986 Enresa undertook the preliminary tasks, the start-up and the performance of the dismantling and decommissioning plan for the Andújar uranium mill Jaén.Aimed at restoring the site and integrating it into the surroundings, the Enresa project...
Activities and Projects > Dismantling and decommissioning of facilities > Dismantling and decommissioning of the Vandellós I nuclear power plant
In accordance with the directives of the International Atomic Energy Agency, the Vandellós I nuclear power plant dismantling and decommissioning project is broken down into the following levelsLevel 1. Preliminary conditioning activities.Following...
Activities and Projects
The emphasis placed by Enresa on RandD has made it possible to improve and optimise each of its processes, technological progress and Spains international position as a reference in radioactive waste management. R and D on radioactive waste Enresa...
Activities and Projects > Dismantling and decommissioning of facilities
From the time at which the uranium is extracted from the deposits until the time at which it is it loaded as fuel at the nuclear power plants, the ore passes through several different sites uranium mines, concentrates factories and fuel assembly...
Safety and the Environment
As is the case for all the companys tasks, the objective of the environmental surveillance plans is to protect the environment and, if necessary, establish corrective measures. Environmental Radiological Surveillance Plans The Environmental...