dormancy

9 resultados para "dormancy"

Activities and Projects > Dismantling and decommissioning of facilities

Dismantling and decommissioning of the Vandellós I nuclear power plant

...was carried out.Following the sealing of the reactor, the greater part of the site was recovered and the 25-year dormancy period began, during which time the reactor will remain confined for its radioactivity to decay prior to complete...

Activities and Projects > Dismantling and decommissioning of facilities > Dismantling and decommissioning of the Vandellós I nuclear power plant

Chronology of the Vandellós I dismantling and decommissioning plan

...facility.Completion of the Materials Declassification Process Test Plan.Initiation of works on infrastructures for the dormancy period.2001.Initiation of shipments of declassified materials to the recycling plants.Assembly of the reactor shroud...

Activities and Projects > Dismantling and decommissioning of facilities > Dismantling and decommissioning of the Vandellós I nuclear power plant

The dismantling and decommissioning of the Vandellós I nuclear power plant step by step

...level radioactive wastes were sent to the El Cabril centralised disposal facility..Most of the site was released...Dormancy period.The reactor shroud must remain as a regulated area under surveillance for 25 years.The reactor shroud must remain as...

Activities and Projects

Dismantling and decommissioning of facilities

...was carried out.Following the sealing of the reactor, the greater part of the site was recovered and the 25-year dormancy period began, during which time the reactor will remain confined for its radioactivity to decay prior to complete...

Activities and Projects > Research and Development

Research centres

...to the decommissioning of nuclear facilities.Work is performed basically in three areas management of the Vandellós I dormancy period, research on technologies, materials and procedures for future dismantling projects and the training of qualified...

Get to Know Us > Enresa Environments

Enresa Environment at Vandellós

...and a guided visit to the installations that once were the Vandellós I nuclear power plant and are now in the dormancy phase.The three-hour scheduled visits are oriented towards the public in general, and students in particular, and are free of...

Get to Know Us

Enresa Environments

...and a guided visit to the installations that once were the Vandellós I nuclear power plant and are now in the dormancy phase.The three-hour scheduled visits are oriented towards the public in general, and students in particular, and are free of...

Activities and Projects

Research and Development

...to the decommissioning of nuclear facilities.Work is performed basically in three areas management of the Vandellós I dormancy period, research on technologies, materials and procedures for future dismantling projects and the training of qualified...

Mestral Technology Centre. Three years of activity PT-03-2007

In 2003, with the completion of the level 2 dismantling of the Vandellós 1 nuclear power plant now in sight, we posed a series of questions aimed at shaping the future of this facility throughout a lengthy phase of dormancy … Detalles

Archivo PDF para descargar Download PDF (4624 KB)