General Information.No of persons collaborating 2,700.Average No of workers 323.Average No of local workers 226.Peak No of workers 420.No of companies involved 63.Average No of companies 30.No of hours of work 2,750,000.Average No of daily tasks...
Activities and Projects > Dismantling and decommissioning of facilities
The Vandellós I nuclear power plant is located in the municipality of Vandellós i L'Hospitalet de L'Infant, in the province of Tarragona. The plant initiated its commercial operation in 1972 under the responsibility of the company Hispano-Francesa...
Enresa is responsible for returning those locations at which there have been nuclear and uranium mining activities to their original state. José Cabrera nuclear power plant decommissioning project The José Cabrera nuclear power plant, located in...